Only for the period from March 23 to May 31 to buy an apartment in a multifunctional residential complex POLARIS Home&Plaza it is possible at the most favorable rate of 24.8 UAH / USD! This promotion applies both to apartments purchased for 100 percent payment and through an installment program. In addition, an additional action "Complete investment security" has been introduced. For those who enter into an agreement during the quarantine period, a full refund is guaranteed without any penalties.

Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.

"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.

We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

Object site: https://polaris.kiev.ua/

ORDER A CALL
Project developers:

The course of construction

Watch construction videos
The second stage of construction:
Section 4.1
  • The monolith is completed, the "flower" -symbol of its readiness is established
  • Brickwork continues at the 26th floor
  • Roof ventilation ducts completed
  • Work has begun on the installation of the roof
  • Windows are installed at the level of 24 floors
  • Laying of heating and water supply pipes in the floor (24th floor)
  • Electricity work continues: installation of the power cable on the valves at the level of 24 floors
Section 3.3
  • Brickwork is performed at the level of the 19th floor
  • Installation of windows and balconies at the level of 4-6 floors
Section 3.2
  • The progress of monolithic works has reached the level of 23 floors
  • Slab contraction joints should intersect at the openings for columns
  • Brickwork is performed at the level of the 12th floor
Section 2.1
  • Preparatory works on installation of railways with the subsequent planned installation of the tower crane are conducted.
Section 3.1
  • Vertical elements are arranged (reinforcement of pylons, installation of pylon formwork) at the level of the 6th floor
Section 2.2
  • Reinforcement of a grid, installation of a timbering of a grid is carried out
The first stage of construction:
Sections 1.1 and 1.2 (16th floor)
  • Arrangement of internal water supply systems is underway - up to the 9th floor
  • The interior decoration (plaster) of the stairs continues - about 50% is done
  • Internal power supply networks are being laid - up to the 15th floor
  • Elevator work continues
  • Installation of floor screeds has started
2020
May
July
August
September
October
November
December
2021
January
February
March
April
May
June
August 2020
September 2020
November 2020
December 2020
January 2021
February 2021
March 2021
April 2021
May 2021
В цілому по комплексу
  • Received technical specifications for LLC "Gradostroy-1" for external power supply.
  • Ordered services for the development of hydraulic calculation for gasification of houses 2.1, 2.2, 3.1, 3.2, 3.3, 4.1 for further obtaining technical specifications for gas
  • Permits were issued for organizing the 2nd arrival at the construction site (approval of the pilot project)