Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.
"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.
We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
Object site: https://polaris.kiev.ua/
The construction of the Polaris Home&Plaza residential complex does not stop for a moment! From the beginning of the month to December 15, the following amount of work was completed here:
Section 4.1 - Work is underway on the facade from the courtyard side - restoration of the adjacency (sealing) of window and door structures to the brickwork. Engineering premises are ready for transfer for equipment installation, equipment delivery is expected.
Section 3.3 - Engineering premises are ready for transfer for equipment installation. We are waiting for equipment delivery.
Section 3.2 - Installation of window structures on the 24th floor has been completed, installation of window structures on the 25th floor has begun.
Section 3.1 - Wall construction continues on floors 10-11.
Section 2.2 – Monolithic works: the installation of the floor slab above the 8th, 9th and 10th floors and the vertical elements of this level have been completed. Work has begun on the installation of the vertical elements of the 11th floor and the reinforcement of the floor slab above the 11th floor.
634.2 cubic meters of concrete were received at the site in two weeks.