Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.
"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.
We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
Object site: https://polaris.kiev.ua/
Active construction is underway at the Polaris Home&Plaza residential complex!
Throughout November 2025, a significant volume of planned work was completed, bringing the site even closer to finalization.
Finishing of walls and installation of doors in technical premises have been completed.
Work on laying floor tiles is ongoing.
Installation of window structures is being performed on the 24th floor.
Monolithic Works: Vertical elements and the floor slab above the 25th floor have been completed.
Wall masonry (or walling/brickwork) on the 8th and 9th floors has been completed.
Wall masonry is continuing on the 10th and 11th floors.
Monolithic Works: Vertical elements and floor slabs above the 6th and 7th floors have been completed.
Vertical elements of the 8th floor have been completed.
Arrangement of the floor slab above the 8th floor is ongoing.
In total, 742.6 cubic meters of concrete were received during the month.