Замовити дзвінок

Ім’я:*
Телефон:*
POLARISHome&Plaza PROMOTIONAL OFFER
POLARIS Home&Plaza: full security of investments at the most favorable rate of 24.8 UAH / USD

Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.

"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.

We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

Object site: https://polaris.kiev.ua/

ЗАМОВИТИ ДЗВІНОК
Девелопери проекту:

Accelerating the pace! Construction progress in February 2026

09.03.2026

February 2026 at the Polaris Home&Plaza residential complex construction site was quite productive.

During the month, a number of important works were completed here, indicating an increase in the pace of construction:

Section 4.1

  • 35% of the installation of insulation with doweling of the main field has been completed.
  • Application of the reinforcing layer with fiberglass mesh installation – 5% completed.
  • Tightness testing of water supply and heating systems up to the 20th floor has been carried out.
  • Pumps for the pump room have been delivered.
  • Installation of external lightning protection outlets has been completed.

Section 3.3

  • Vapor barrier of external window installation joints is 95% complete.
  • 15% of the facade insulation installation with doweling of the main field has been completed.
  • Installation of equipment in ITP No.1 has been completed; the equipment is being prepared for testing. Installation of boiler house equipment No.1 is ongoing.
  • Delivery of apartment entrance doors is ongoing.

Section 3.2

  • Brickwork on cold transition areas is ongoing.
  • Suspended platforms for facade works have been installed.
  • 10% of the vapor barrier of external window installation joints has been completed.
  • 5% of the facade insulation installation with doweling of the main field has already been completed.

Section 3.1

  • Masonry of walls and partitions on the 11th floor has been completed; work continues on the 12th floor. Masonry from the 13th to the 17th floors has begun.
  • Elevator equipment has been delivered.

Section 2.2

  • Monolithic works: the floor slab between the 12th and 13th floors and vertical structural elements have been completed. Installation of vertical elements of the 14th floor is ongoing.

In total, 512 m³ of concrete were delivered and used during the month.