Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.
"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.
We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.
Object site: https://polaris.kiev.ua/
Everywhere you look, around Polaris Home & Plaza, spring announces its arrival. From the upper floors, you can see how the amazing panoramas of Obolon 🇺🇦 are washed by the sun
This is exactly what the horizon of our dreams is – bright and convincing. Therefore, this cheerful mood is already felt at the construction site.
Follow us for progress. Here is the progress of work in March:
Section 4.1
✓ façade works are underway
✓ Insulation of loggias continues
✓ The wiring of the electrical network in the section and the installation of switchboards on the floors has been completed
✓ at the final stage of masonry of brick walls on the first and second floors
✓ reinforcement of the floor of the elevator hall on the ground floor is in progress
✓ Work is underway to insulate cold passages
Section 3.3
✓ façade work is progressing
✓ Installation of elevator equipment continues: the cabin and portals of the freight and passenger elevator are installed, guides are mounted in the shafts of passenger elevators
✓ Installation of risers and apartment wiring of cold, hot water and heating networks is in progress
✓ The wiring of the power grid in the section continues
✓ bricklaying on the first floor is being completed, work is underway on the second floor
✓ A heating main is being installed from the ground floor to the roof boiler room
✓ Cutting of concrete holes for the installation of utilities has begun
✓ Installation of window structures on the third floor continues
Section 3.2
✓ Brick work is underway
Section 1.1. and 1.2
✓ Monolithic work continues on the installation of a part of the retaining wall of the underground parking
✓ Decoration of common areas is in progress