Angelica Sahakyan, project manager POLARIS Home&Plaza, noted that the developers of the project are companies Perfect Group and Citex Development – have sufficient financial resources to ensure the smooth construction of the residential complex in accordance with the work schedule.

"Every day the construction is gaining momentum. And for those buyers who keep their savings in foreign currency, the proposed shares allow you to become the owner of an apartment with an additional benefit of up to 10% only on the exchange rate difference. In addition, buyers are guaranteed complete investment security, "she said. The number of apartments involved in the action is limited.

We will remind, the company Perfect Group and Сitex Development began completion of the frozen facility on the street. Kulzhenko family, 22, and the construction of a multifunctional residential complex. The area of land allocated for construction is 2.9 hectares. The construction customers are PE PE "Budinvestmontazh" and LLC "Gradobud 1". General contractor of construction: LLC "Budpidryad".

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

The residential complex will be built on a monolithic-frame technology with external duties and internal walls made of red solid brick and insulated with mineral wool. Delivery of the first stage of construction POLARIS Home & Plaza scheduled for the second quarter of 2022. The completion date of the entire project is the second quarter of 2023.

Object site: https://polaris.kiev.ua/

ЗАМОВИТИ ДЗВІНОК
Девелопери проекту:

Construction progress in February 2024

15.02.2024

We walk to spring with inspiration, we see off the winter with joy.

Despite the cold period, the work has progressed significantly: the facades are becoming more expressive, the glazing is progressing, doors have been installed in the section with the highest readiness, and much more. The team successfully brought to the "plus" even those tasks that seemed extremely difficult during the war 🇺🇦

We continue to work, summing up the results and reporting with fresh photos on the topic:

Section 4.1

✓ façade works continue

✓ Insulation of loggias continues

✓ wiring of the electrical network in the section and installation of switchboards on the floors

✓ brick walls on the first and second floors are being bricked

Section 3.3

✓ façade work is progressing

✓ Installation of elevator equipment continues

✓ Plumbing work is underway

✓ Electrical network wiring in the section is in progress

✓ bricklaying continues on the first and second floors

Section 3.2

✓ Brick work continues

Section 1.1. and 1.2.

✓ Monolithic works are underway to install a part of the retaining wall of the underground parking